One Site preparation includes site cleaning, arrangement, leveling, level confirmation, temporary perimeter fence installation, excavation and other necessary works.<br>Two Earthwork in laydown area, sea water pump house (including fire fighting sea water pump house) and green belt area on the east side of the plan will coordinate with related manufacturers of the storage tank plan to conduct earthwork dispatching. The schematic diagram of borrow area is shown in Annex 28.<br>Three The temporary perimeter fence of all facilities shall be provided by the contractor.<br>